Our Workshops / Fishfarm / opteam us Web site


Description

 
 
This workshop allows us to discover, in situation and in a simple and natural way, the main techniques of project management, to examine them and come to an easy practice.
It happens around the «Fishfarm» simulation game the theme of which is the construction of a fish farm. The participants adopt operational roles (project leader, engineer, planner, cost controller, quality manager).
The complete life cycle of an industrial project thus goes ahead in five phases.
 

Targets

 
 
  • Discovering the working of project organisations and learning to formalise communication (files, reviews, etc.) and commitments between the parties
  • Acquiring a basic procedure of a project and knowing how to adapt it in function of the type of project
  • Having an overall view over the main techniques of Project Management to be capable of using them advisedly
  • Learning to find the best compromise between cost, lead time and quality, and learning to justify choices
  • Knowing how to get control of the project configuration and manage developments
  • Acquiring general knowledge in matters of ensuring quality of projects

Public concerned

 
 
  • Project leaders
  • Members of Project Teams
  • Planners
  • Project Managers
  • Quality Managers

Programme

 
 
Organisation
  • Analysis of the opportunity of the project and its targets
  • Project environment: the parties
  • Analysis of management requirements:
  • Management Specifications
  • Examination of the contractual context
Preliminary study
  • Study of possible scenarios
  • Choice of a scenario and justification of the choice
  • Analysis of overall project risks
  • Elements of a business plan
  • Drawing up the project plan (phases, stages, milestones, deliverables, reviews)
Detailed study
  • Defining the need
    Functional analysis, functional specifications
  • Structuring the project
    Definition of the Work Breakdown Structure (WBS), exhaustive breakdown of the project into tasks, definition of responsibilities, writing up a Work Package Sheet
  • Project planning
    Construction of planning : the PERT, the GANTT, rare resources - slow supplying presentation of project management software Demonstration with the MS-PROJECT software
  • Establishment of reference planning
    Reduction of lead time, identification and analysis of critical points, establissement of reference lead time
  • Establishment of the budget
    Estimation, quote, financing, establishment of the initial budget, economic summary, calculation of ROI
  • Review and feasibility
    Justification of project options in relation to QCD targets, presentation of the project plan
Development
  • Organisation of developments
    Technical choices, configuration management, qualityu management of deliverables, contingency and change management, signing a contract with a subcontractor
  • Meeting and follow-up of status
    Detailed planning, organising and conducting a project review, physical status, S curb, analysis of variations, trends, estimation to the end, simulation and reprogramming
  • Communication and dashboard
    Communication plan, contents of a dashboard
Transfer, Project result
  • Organising the transfer to the operator
  • Capitalising experience
 
 
 
 